Fire Protection for Exposed
Structural Steel
FAIME Construction Inc. applied intumescent fireproofing to structural steel in a York Region warehouse in Newmarket, Ontario, as a subcontractor, between March and April 2026. The scope covered selected beams, columns and a 1,300 sq ft steel deck, on a project of 3,000 sq ft, as part of an upgrade that will add office space to the building. The coatings were Sherwin-Williams Firetex® FX5120 for a 1-hour rating and Firetex® FX5090 for a 2-hour rating. Both are water-based, thin-film intumescent coatings, and they were applied by air spray and hand roller in multiple coats, with dry film thickness verified and recorded at inspection. The work was completed on schedule, within budget and with zero safety incidents, while the warehouse remained in operation.Intumescent fireproofing & industrial coatings · GTA & York Region · 15+ years' trade experience · WSIB Active · $2M CGL · 2-year workmanship warranty
Project Overview
York Region is upgrading its Newmarket warehouse so that office space can be added in the future. Exposed structural steel that will support or sit alongside occupied office space needs a defined fire-resistance rating. FAIME Construction was contracted to provide that fire protection to the selected structural elements: beams, columns and a 1,300 sq ft steel deck.
The work ran from March to April 2026 with a crew of up to four, and fireproofing was the only trade on FAIME's scope. Throughout the project, the warehouse continued to operate around the work areas.
Why an Intumescent Coating
Intumescent fireproofing is a thin coating that looks like paint under normal conditions. When it is exposed to the heat of a fire, it expands into a thick, insulating char that slows the rate at which the steel heats up, preserving its load-bearing capacity for the rated period. Unlike cementitious spray fireproofing, it leaves the steel visible with a clean, decorative finish, which suits exposed steel in a space that will become offices.
The products specified were Sherwin-Williams Firetex® FX5120 for the elements requiring a 1-hour rating and Firetex® FX5090 for those requiring a 2-hour rating. Both are water-based, thin-film intumescent coatings designed for exposed interior structural steel.
Site Assessment & Preparation
The work began with an inspection of the warehouse to confirm which beams, columns and deck areas were to be protected, and with coordination with the client and the other contractors on site. The steel surfaces were then cleaned and prepared for coating. Surrounding areas, equipment and anything not being coated were masked off to protect them from overspray, an important step in a building where operations continued around the work.
Application in Measured Coats
With intumescent coatings, the fire rating depends on thickness. A rating is achieved only when the dry film thickness specified for each steel section is reached. The coating was applied by air spray in combination with hand rolling to achieve even coverage across flanges, webs, connections and the deck. It was built up in multiple coats, applied approximately eight hours apart so that each layer could cure properly before the next. The schedule required multiple applications per day.
Thickness Inspections & Documentation
Coating thickness was checked regularly as the work progressed to confirm even application and to verify that the required thickness was being achieved for each rating. All inspection readings were recorded for client reporting. After the final coat had cured, a final walk-through was completed and the client received the supporting documentation: inspection reports and the material certifications for the products applied, along with guidelines for ongoing inspection and any future repairs.
Safety in an Operating Warehouse
The work areas were fenced and controlled, crews worked to the site's safety protocols with the appropriate personal protective equipment, and applications were scheduled to keep disruption to the warehouse's ongoing operations to a minimum. The project was completed on schedule, within budget and with zero safety incidents.
For General Contractors, Facility Owners & Property Managers
FAIME Construction applies intumescent fireproofing to structural steel in warehouses, industrial buildings and commercial conversions, both as a subcontractor to general contractors and directly for facility owners. We work to the specified products and thicknesses, record our inspections, and hand over the documentation. Our crews are WSIB Active and covered by $2M general liability insurance, and certificates are available on request.
Bare Steel to Rated Finish
Real photographs of the structural steel before and after the intumescent coating was applied, taken in March and April 2026.













Scope Breakdown
Assessment & Preparation
- Beams, columns and deck areas identified on site
- Coordination with the client and other contractors
- Steel surfaces cleaned and prepared
- Masking and overspray protection
Intumescent Application
- Firetex® FX5120 for 1-hour rated elements
- Firetex® FX5090 for 2-hour rated elements
- Air spray combined with hand rolling
- Multiple coats, approximately 8 hours apart
Inspection & Quality Control
- Dry film thickness checked as work progressed
- Even coverage on flanges, webs and connections
- All readings recorded for client reporting
- Curing confirmed before the final walk-through
Handover & Documentation
- Final walk-through with the client
- Inspection reports provided
- Material certifications provided
- Guidelines for ongoing inspection and repair
Intumescent Fireproofing FAQ
What is intumescent fireproofing?
A thin coating applied to structural steel that looks like paint under normal conditions. When exposed to the heat of a fire, it expands into a thick, insulating char that slows the rate at which the steel heats up, helping it keep its load-bearing capacity for the rated period. Unlike cementitious spray fireproofing, it leaves the steel visible with a clean, decorative finish.
How is the fire rating of an intumescent coating achieved?
Through thickness. Each steel section has a specified dry film thickness for its required rating, and the rating is only achieved when that thickness is reached. Here the coating was built up in multiple coats approximately eight hours apart, thickness was checked as the work progressed, and every reading was recorded for client reporting.
What intumescent products were used on this project?
Sherwin-Williams Firetex® FX5120 for elements requiring a 1-hour fire-resistance rating, and Firetex® FX5090 for elements requiring a 2-hour rating. Both are water-based, thin-film intumescent coatings for exposed interior structural steel.
Can fireproofing be applied while a warehouse stays in operation?
Yes, with planning. Here the work areas were fenced and controlled, surrounding areas and equipment were masked against overspray, and applications were scheduled to minimise disruption to the warehouse's ongoing operations. The project was completed on schedule with zero safety incidents.
What documentation is provided after intumescent fireproofing?
On this project the client received the recorded thickness inspection reports, the material certifications for the products applied, and guidelines for ongoing inspection and any future repairs, following a final walk-through.